MAROOCHY RIVER · GRANNY FLAT BUILD
A Maroochy River granny flat,
from site prep to first floor.
Follow this granny flat build in Maroochy River on the Sunshine Coast, from site preparation and drainage to posts, bearers, joists and the first Secura flooring sheets.
LOCATION
Maroochy River
Sunshine Coast
PROJECT
Granny flat build
11 workdays, 7–28 Oct 2026
FLOOR SYSTEM
Bearers and joists
Secura flooring started
STATUS
Under construction
Last updated 28 October 2026
THE STORY / MAROOCHY RIVER
A granny flat taking shape.
The Shed House is building this granny flat in Maroochy River on the Sunshine Coast. The project shows our Sunshine Coast builders at work, from site preparation and drainage through to subfloor construction.
Work began on 7 October with site preparation: cutting back the batter (the sloped bank of earth), boring the post holes and pouring concrete bases.
The record covers 11 documented workdays between 7 and 28 October 2026, following site preparation, drainage and floor construction through to the first flooring sheets.
By 28 October, bearers and joists were in place, triple grips and strap bracing had been installed, and Secura flooring had started. The photographs below capture the work recorded so far.
THE WORK BEHIND THE PROGRESS
From groundworks to structural details.
Site preparation, drainage and structural connections all feature in the October work record.
01 / SITE PREPARATION
Preparing the ground.
Our crew reorganised the site, cut back the batter and bored the post holes, placing concrete in the base of each before the posts went in.
02 / POSTS AND FOOTINGS
Setting out the supports.
Floor and post heights were set and checked, posts and brackets prepared, and footing edges trimmed so every post connection sits properly.
03 / DRAINAGE AND BACKFILL
Working behind the block wall.
Agricultural (ag) pipe and PVC pipe went into trenches behind the block wall, followed by geofabric, backfill and batter shaping. A small spoon drain (a shallow channel that directs surface water) was also formed.
04 / FLOOR STRUCTURE
Bringing the floor together.
Bearers and joists went in, then joist blocking and a trimmer framing the wet-area step-down, which lowers the floor where bathroom tiles will go. Triple grips and strap bracing followed on 28 October.
05 / FLOORING STARTS
The first sheets go down.
Triple grips and strap bracing were installed on 28 October, followed by the start of Secura flooring. The next recorded step was to continue flooring.
COMPLETED SO FAR
What's done to date.
The October updates record the following work, from early ground preparation to the start of flooring.
- Site preparation and batter cutting
- Bored holes and concrete bases
- Post installation, plumbing and bracing
- Agricultural and PVC drainage pipework
- Geofabric, backfill and a spoon drain
- Bearers, joists and wet-area step-down framing
- Triple grips and strap bracing installed
- Secura flooring started
THE CONSTRUCTION RECORD
Watch the build take shape.
Eight milestones across 11 documented workdays, from 7 to 28 October 2026. The final day records triple grips, strap bracing and the start of flooring.
01 · DAY 1 · 7 OCT 2026
Site preparation
The site was reorganised, the batter cut back, and post holes bored with concrete placed in the base of each.
02 · DAYS 2–4 · 8–12 OCT 2026
Posts and bracing
Floor height was set and posts and brackets prepared. Posts were then stood, plumbed (set vertical), braced and concreted, and a materials delivery arrived on 12 October.
03 · DAY 5 · 14 OCT 2026
Drainage and backfill
Trenches were dug and agricultural and PVC pipe were laid. Work behind the block wall included geofabric, backfill, batter shaping and a small spoon drain.
04 · DAY 6 · 15 OCT 2026
Post heights and brackets
Post heights were laser-checked, cutting and bracket preparation continued, and posts began going up along the block wall. Cladding sheets and flashings were delivered.
05 · DAYS 7–8 · 20–21 OCT 2026
Bearers in place
Posts were cut and the joist layout was marked. Bearers were prepared and installed, and the final post was fixed to its footing.
06 · DAY 9 · 26 OCT 2026
Joist installation begins
Back-to-back bearers (paired beams for extra strength) went in, and joist installation began.
07 · DAY 10 · 27 OCT 2026
Joists and wet-area framing
Joists, blocking and the wet-area step-down trimmer went in. The joists were plumbed and screwed off and the set-out profiles removed before a storm stopped work.
08 · DAY 11 · 28 OCT 2026
Flooring starts
Triple grips and strap bracing were installed, then Secura flooring was started.
WHAT'S NEXT
Finishing the floor.
Next up is laying the rest of the Secura flooring. We'll add new milestones and photos here as the build progresses.
THE FINISHED VISION
A glimpse of the finished Maroochy River granny flat.
These concept renders offer a preview of the planned interiors, with furniture and styling digitally added to help bring the design to life.
We'll share real photographs as the build progresses and the interiors take shape.