BLACK MOUNTAIN ยท BUILD IN PROGRESS

A Black Mountain new home,
from footings to floor.

We're building a new home in the Sunshine Coast Hinterland. Follow the structure go up stage by stage, from the first footings to the veranda posts, with site photos throughout. Last updated 28 October 2026.

LOCATION

Black Mountain

Sunshine Coast, QLD

PROJECT

Elevated home build

Sunshine Coast Hinterland

BUILD STAGE

Floor platform

Flooring and veranda posts underway

STATUS

Under construction

Last updated 28 October 2026

THE STORY / BLACK MOUNTAIN

Getting the structure right
from the ground up.

Every home on a hinterland block starts below the floor. At Black Mountain, our crew began with the piers, cleaning, compacting and measuring every hole before the concrete footings went in, then stood and braced the posts that carry the whole structure.

From there the floor came together in layers: bearers, perimeter joists, the main joist field and, from mid-October, the flooring itself. Rain interrupted several workdays along the way, but the sequence kept moving.

By 28 October the floor platform was well advanced and the veranda posts were stood, plumbed and welded. We'll add new milestones here as the build moves into its next stage.

THE STRUCTURE TAKES SHAPE

Measured heights.
Steady progress.

Five stages make up the structure this home will stand on. Here's what each one involves and why it matters.

01 / PIERS & FOOTINGS

Preparing the support points.

Each pier hole was cleaned, compacted and measured for depth before concreting, with posts prepared and braced ready to set. Footings are never seen again, so they're checked first.

02 / POST INSTALLATION

Checking every height.

Our crew laser-checked every post height, then cut, stood, plumbed (set perfectly vertical) and braced each post. Accurate heights here are what give you a level floor later.

03 / BEARERS & JOISTS

Connecting the floor structure.

Bearers are the main beams across the posts; joists run across the bearers to carry the floor. Under-bearers, bearers and perimeter joists went in first, then the main joists were laid, aligned and braced.

04 / FLOORING

Forming the platform.

Flooring started once the triple grips (connectors that tie each joist to its bearer) and wall joists were finished. The platform grew steadily from there.

05 / VERANDA POSTS

Preparing and welding the posts.

Posts and sleeves were cut to size, bracket positions marked out with a laser, and the veranda posts stood, plumbed and welded in place.

COMPLETED SO FAR

What's done
to date.

A quick checklist of the work completed up to 28 October.

  • Pier cleaning and depth checks
  • Concrete footings
  • Post preparation and installation
  • Under-bearers and bearers
  • Perimeter joists and main joists
  • Triple grips and joist bracing
  • Flooring installation
  • Veranda post preparation and welding

THE CONSTRUCTION RECORD

Watch the structure take shape.

Eight milestones from late September to 28 October, from the first footings to the veranda posts.

Posts, structural members and scaffolding in the Black Mountain build record.

01 ยท 29 SEP โ€“ 2 OCT 2026

Preparing footings & posts

Piers were prepared and concreted, heights checked, and the first posts stood and braced.

View along the structural line from the scaffold.

02 ยท 6 โ€“ 7 OCT 2026

Completing the post lines

The last four posts were stood and concreted, heights were checked again, and the first under-bearers went in.

Bearer and perimeter framing with straightening joists.

03 ยท 8 โ€“ 9 OCT 2026

Bearers & perimeter joists

The remaining bearers and perimeter joists were completed, and straightening joists were laid.

Joist field stood, aligned and braced within the scaffold.

04 ยท 12 โ€“ 14 OCT 2026

Joists & triple grips

The main joists were laid, plumbed and braced while the triple grips went in.

Flooring progress across the main platform, with an opening retained in the joist field.

05 ยท 15 โ€“ 20 OCT 2026

Flooring begins

With the triple grips and wall joists finished, the first flooring went down and spread across the platform.

Wide view of the expanded floor deck and remaining open joist area.

06 ยท 21 โ€“ 26 OCT 2026

Flooring continues

Rain stopped work at midday on 21 October, but flooring was back underway by 26 October.

Veranda posts stood along the platform edge with temporary yellow-tongue fall protection.

07 ยท 27 โ€“ 28 OCT 2026

Veranda posts installed

Veranda posts were stood, plumbed and welded. Yellow-tongue flooring sheets were laid over open areas as temporary fall protection, keeping the crew safe while working at height.

WHAT'S NEXT

Flooring underway. Veranda posts in place.

Finishing the flooring and bracket work and continuing the welding, weather permitting.