A Black Mountain new home, from footings to roof.

We’re building an elevated home in the Sunshine Coast Hinterland. Follow the build from the first concrete footings to the finished roof sheeting and the start of wall wrapping, with site photos along the way. Last updated 20 November 2026.

Location
Black Mountain
Sunshine Coast, QLD
Project
Elevated home build
33 documented workdays 29 September – 20 November 2026
Build stage
Wall wrap and window preparation
Roof sheeting installed
Status
Under construction
Last updated 20 November 2026

BLACK MOUNTAIN / FROM THE GROUND UP

Getting the structure right from the ground up.

Every home on a hinterland block starts below the floor. At Black Mountain, our crew began with the piers, cleaning, compacting and measuring every hole before the concrete footings went in, then stood and braced the posts that carry the whole structure.

From there the floor came together in layers: bearers, perimeter joists, the main joist field and, from mid-October, the flooring itself. Rain interrupted several workdays along the way, but the sequence kept moving.

With the floor platform complete, the crew finished the underfloor bracing and stood, braced and plumbed the wall frames. The roof sheets were installed and secured by 16 November. By 20 November, the team was wrapping the walls, had finished the trims above the windows and was preparing openings and thresholds for the windows and sliding doors.

Digital renders and staging have been used to showcase this building.

Watch the structure take shape.

Follow 12 milestones from late September to 20 November, from the first footings to roof sheeting, wall wrapping and window preparation.

  1. 01 · 29 SEP – 2 OCT 2026

    Preparing footings & posts

    Piers were prepared and concreted, heights checked, and the first posts stood and braced.

  2. 02 · 6 – 7 OCT 2026

    Completing the post lines

    The last four posts were stood and concreted, heights were checked again, and the first under-bearers went in.

  3. 03 · 8 – 9 OCT 2026

    Bearers & perimeter joists

    The remaining bearers and perimeter joists were completed, and straightening joists were laid.

  4. 04 · 12 – 14 OCT 2026

    Joists & triple grips

    The main joists were laid, plumbed and braced while the triple grips went in.

  5. 05 · 15 – 20 OCT 2026

    Flooring begins

    With the triple grips and wall joists finished, the first flooring went down and spread across the platform.

  6. 06 · 21 – 26 OCT 2026

    Flooring continues

    Rain stopped work at midday on 21 October, but flooring was back underway by 26 October.

  7. 07 · 27 – 28 OCT 2026

    Veranda posts installed

    Veranda posts were stood, plumbed and welded. Yellow-tongue flooring sheets were laid over open areas as temporary fall protection, keeping the crew safe while working at height.

  8. 08 · 29 OCT – 3 NOV 2026

    Flooring complete and walls take shape

    The crew finished the floor platform and temporary fall protection, then began standing the wall frames. Underfloor bracing was complete by 3 November.

  9. 09 · 4 – 6 NOV 2026

    Wall frames secured

    The crew finished standing, bracing and plumbing the wall frames, then completed the frame tie-downs and installed the boxed beams.

  10. 10 · 9 – 12 NOV 2026

    Rafters and roof battens

    The crew finished the outriggers, installed the rafters and secured them with tie-downs and strap bracing. They finished the roof battens and lifted the sheets into position.

  11. 11 · 13 – 16 NOV 2026

    Gutters and roof sheeting

    The crew finished the fascia and installed the gutters on 13 November. By 16 November, all roof sheets were in place and screwed down.

  12. 12 · 17 – 20 NOV 2026

    Wall wrap and window preparation

    The crew started the ceiling battens and installed bathroom frames. They also worked on the vermin seal. By 20 November, wall wrapping was underway, the trims above the windows were finished and openings for windows and sliding doors were being prepared.

  13. WHAT'S NEXT

    Finishing the wall wrap and moving on to windows.

    With the roof sheets secured and the openings taking shape, the crew plans to finish the wrap before moving on to the windows.

COMPLETED SO FAR

What's done to date.

A quick checklist of the work completed up to 20 November.

  • Pier cleaning and depth checks
  • Concrete footings
  • Post preparation and installation
  • Under-bearers and bearers
  • Perimeter joists and main joists
  • Triple grips and joist bracing
  • Flooring installation
  • Veranda post preparation and welding
  • Underfloor bracing
  • Wall framing, frame tie-downs and boxed beams
  • Rafters, rafter tie-downs and roof battens
  • Fascia and gutters
  • Roof sheeting installed and secured