Built from the ground up. Finished for hinterland living.
A compact shed house brought to life in the Sunshine Coast hinterland.
Follow the journey from drilled piers to handover.
- Location
- Maleny region
- Sunshine Coast Hinterland
- Project
- Compact shed house
- Floor system
- Elevated steel
- Pier, post and bearer construction
- Status
- Completed home
- Handover recorded November 2026
Maleny region / From the ground up
A compact footprint. A complete home.
Set among the greenery of the Sunshine Coast hinterland, this project began with drilled piers and an elevated post-and-bearer floor system.
The structure progressed through steel framing, roof panels, weatherproofing and mixed external cladding before the deck, ramped entry and balustrade completed the outside.
Inside, insulation and plastering were followed by cabinetry, tiling, painting, flooring, electrical and plumbing fit-off to create a compact, fully finished home.
Watch the home take shape.
Twenty documented milestones, from drilled piers on 30 June to handover on 11 November 2026.
01 · DAY 1
Drilling piers
Preparing the foundations and posts for the elevated floor system.
02 · DAYS 2–3
Posts, bearers & joists
The raised steel subfloor structure takes shape above the site.
03 · DAY 4
Installing flooring
Secura flooring creates the platform for the framed structure above.
04 · DAYS 5–6
Wall frames & roof panels
Steel walls, beams and roof framing establish the form of the home.
05 · DAYS 7–9
Bracing, wrap & battens
Bracing, tie-downs, wall wrap and roof battens prepare the shell for lock-up.
06 · DAY 10
Windows & doors
Windows and the glass slider are fitted into the wrapped steel frame.
07 · DAY 11
Cladding begins
Head flashings and cavity closers go in and the corrugated metal cladding starts to enclose the home.
08 · DAYS 12–13
Cladding continues
Cladding wraps around the window openings and the eave ceiling battens are fixed.
09 · DAY 14
Roofing & fascia
Roof sheets, roof flashings, fascia and gutters make the home weathertight.
10 · DAYS 15–17
Soffits, flashings & weatherboards
Outdoor ceilings, barge flashings and weatherboard cladding finish the outer shell.
11 · DAYS 18–20
Deck & ramp
Hardwood decking and a gently sloping ramp create a step-free way in.
12 · DAY 21
Handrail & balustrade
Stair treads, deck fascia and the balustrade complete the outside of the home.
13 · FIT-OUT
Insulation & plastering
With the walls insulated, plasterboard lines the open-plan living area ready for finishing.
14 · FIT-OUT
Fix-out
Window reveals, architraves, doors and skirting are fitted throughout.
15 · FIT-OUT
Cabinetry
The sage-green kitchen goes in, with a window splashback and stone-look benchtop.
16 · FIT-OUT
Tiling
Large-format tiles finish the bathroom floor and the walk-in shower.
17 · FINISHES
Painting
Paint finishes the interior walls, weatherboards, eaves and trims.
18 · FINISHES
Flooring & electrical fit-off
Timber-look flooring is laid and the lights, fans and power points are fitted off.
19 · FINISHES
Plumbing fit-off
Basins, tapware, the toilet and shower fittings are connected.
20 · HANDOVER
Wastewater system & handover
The on-site wastewater treatment system is installed and the finished home was handed over on 11 November 2026.
One coordinated project
From the first pier to the final fit-out.
The Shed House coordinated the structural build, exterior completion and internal fit-out through a clearly documented sequence of work.
- Drilled pier and post foundations
- Bearers, joists and Secura flooring
- Steel wall and roof framing
- Bracing, tie-downs and weatherproofing
- Windows, doors and mixed external cladding
- Deck, ramped entry, handrail and balustrade
- Internal finishes and trade fit-off
- Wastewater treatment system installation
Your block. Your possibilities.
Let’s build something that belongs on your block.
Tell us about your site, the way you want to live and the shed house you have in mind. Our team can discuss the next steps for your project.