Built above the slope. Open to the trees.
A compact hillside build on a suspended steel floor.
Follow the journey from site set-out to handover.
- Location
- Peachester
- Sunshine Coast Hinterland
- Project
- Backyard Studio
- Floor system
- Suspended steel
- Raised above the hillside
- Status
- Completed build
- Handed over 6 November 2026
Peachester Studio / From the ground up
From the first set-out to the final handrail.
Built on an elevated steel platform, this Peachester studio showcases our approach to Sunshine Coast studio construction. Combining lightweight steel framing, generous glazing and durable exterior finishes, the design works with the natural slope of the site to create a contemporary studio that sits comfortably within its surroundings.
A studio built for its site
Peachester's sloping blocks require a builder who understands the challenges of elevated construction and working with the natural landscape. With experience building on challenging Sunshine Coast hinterland sites, The Shed House takes a considered approach to site levels, access and structural design. The result is a studio that works with the slope rather than against it, making the most of the land while minimising unnecessary site disturbance.
01 · DAY 1
Site survey
The survey marked out the building footprint.
02 · DAY 2
Excavate footings
The crew bored and cleaned the pier holes, then set the bases.
03 · DAY 3
Install scaffolding
The crew erected scaffolding around the footprint to provide access for the elevated work.
04 · DAY 4
Install posts
The crew stood and braced the tall steel posts, then completed the concrete work.
05 · DAY 5
Install bearers
The crew cut the posts to height and fitted the steel bearers for the suspended floor.
06 · DAY 6
Install joists
Floor joists and blocking prepared the steel platform for the sheet flooring.
07 · DAY 7
Install flooring
The crew laid the sheet flooring and began setting out the walls on the new platform.
08 · DAY 8
Install wall frames
The crew stood the light steel wall frames and secured them with tie-downs and bracing.
09 · DAY 9
Install beams and rafters
Steel beams and rafters established the single-slope roofline.
10 · DAY 10
Install sarking and fascia
The crew installed the fascia and wrapped the building ahead of roofing and cladding.
11 · DAY 11
Install roof sheets
The crew fixed the metal roof sheets and installed the gutter and its flashing.
12 · DAY 12
Install windows, doors and initial cladding
The crew fitted the windows and glazed doors, finished the soffits and started the exterior cladding.
13 · DAY 13
Install wall cladding
Wall cladding continued, and the crew prepared cavity battens for the Weathertex sections.
14 · DAY 14
Install flashings
The crew fitted flashings around openings and along the wall corners and roof edges.
15 · DAY 15
Complete Weathertex cladding
The crew finished the Weathertex cladding and fitted trim and flashings around the sliding doors.
16 · DAY 16
Install barges
The crew fitted the remaining barge flashings along the roof edges.
17 · DAY 17
Install decking
The crew laid and fixed the timber decking, then finished the deck fascia.
18 · DAY 18
Install handrail
The crew fitted and oiled the timber blocking for the rear handrail and finished the rear balustrade.
19 · DAY 19
Complete the front balustrade
The crew finished the front handrail and fitted the balustrade cables ahead of handover.
20 · INTERIOR FINISHING
Interior plastering
By early October, plasterboard lined the walls and ceiling.
21 · HANDOVER
Front view
The Shed House handed over the build on 6 November 2026. The owner praised the crew’s politeness and site tidiness.
22 · HANDOVER
Hillside view
From the side, you can see how the steel posts lift the building and timber deck above the natural slope.
Scope of works
The Shed House scope of works.
The Shed House delivered a complete design and construction service, including:
- Building plans, site reports and building approval
- Site set-out and pier footings
- Scaffolding and elevated steel posts
- Suspended steel bearers, joists and sheet flooring
- Lightweight steel wall and roof framing
- Colorbond roofing, windows and glazed doors
- Colorbond and Weathertex cladding
- Timber decking, handrails and wire balustrades
- Insulation and plastering
- Painting and electrical works
- Flooring and interior finishes
- Final clean and handover