A steel frame home in Pomona, from slab to handover.
Follow this home from a freshly cleared block to the day the owners received the keys: slab, steel frame, lock-up on Day 27 and seven stages of interior fix-out, shown step by step.
- Location
- Pomona
- Sunshine Coast Hinterland
- Project
- Two-bedroom home
- 90 m² internal floor area
- Floor system
- Concrete slab-on-ground
- Steel frame on a reinforced slab
- Status
- Completed build
- Handed over 9 October 2026
Pomona home / From the ground up
One home, every stage of the build.
Built on a reinforced concrete slab, this two-bedroom Pomona home pairs steel framing with Colorbond and fibre-cement cladding. Inside, sage-green kitchen cabinetry and timber-look flooring give the home a warm, understated finish. Follow the build from site preparation through to handover.
From the building pad to handover.
From preparing the pad to handing over the keys. Fix-out stages are numbered in order rather than by day.
01 · DAY 1
Preparing the building pad
We cleared the vegetation and formed the building pad the home would sit on.
02 · DAY 2
Positioning under-slab plumbing
Plumbing went in beneath the future floor first, because it can’t be moved once the concrete is poured.
03 · DAY 3
Preparing the slab area
The slab area was prepared, ready for boxing, reinforcement and concrete.
04 · DAYS 4–5
Installing boxing and reinforcement
Boxing, the formwork around the edge, set the slab’s shape, and steel mesh went in to strengthen the concrete.
05 · DAY 6
Pouring the concrete slab
The concrete pour created the foundation the rest of the home is built on.
06 · DAYS 7–8
Installing the steel wall frames
Our team stood the steel wall frames on the slab, then connected and secured them ready for the roof.
07 · DAYS 9–11
Building the roof structure
Rafters, tie-downs and bracing formed the roof structure, with the tie-downs anchoring the roof to the frame. Scaffolding gave safe access around the home.
08 · DAYS 11–12
Installing fascia and guttering
Fascia went on along the roof edges, followed by the gutters and their flashings.
09 · DAYS 13–14
Installing the roof
The roof sheets went on and were fixed down, putting the main roof over the home.
10 · DAYS 15–16
Lining the soffits
Soffit lining finished the underside of the eaves.
11 · DAY 17
Wrapping the wall frames
Sarking, a protective wrap that helps keep moisture out of the walls, went around the steel frame ready for cladding.
12 · DAYS 18–20
Installing the Colorbond wall cladding
Corrugated Colorbond wall cladding started closing in the external walls.
13 · DAYS 21–24
Adding cavity battens and fibre-cement cladding
Cavity battens went on to hold the fibre-cement sheets and leave a drainage gap behind them. The sheets then finished the remaining walls.
14 · DAYS 25–26
Completing barges and flashings
Barge and flashing details sealed the roof edges, corners and joins, the last external work before lock-up.
The fix-out, stage by stage.
Seven stages, in the order the trades worked, then handover.
01 · FIX-OUT
Plaster, doors and trims
With the plaster finished, our carpenters fitted the internal door jambs, architraves, doors and handles. The rooms were then cleared of plaster dust and cleaned, ready for the next trades.
02 · FIX-OUT
Kitchen cabinets and vanity
The kitchen cabinets and bathroom vanity went in next. The kitchen features soft green cabinetry with black handles, drawers, pantry storage and spaces for the appliances.
03 · FIX-OUT
Paint throughout
Walls, ceilings, internal doors and trims were painted in a light, consistent finish, giving the interior a clean look before the final fixtures and surfaces went in.
04 · FIX-OUT
Kitchen benchtops
Light-coloured benchtops were fitted around the kitchen cabinetry in a wraparound layout, with room for food prep and the sink built in.
05 · FIX-OUT
Bathroom tiling and fixtures
The bathroom floor and shower walls were tiled in a neutral stone-look finish. Then the plumbing fixtures were installed.
06 · FIX-OUT
Timber-look vinyl plank flooring
Warm timber-look vinyl plank flooring runs through the kitchen, living areas and bedrooms, meeting the tiled bathroom areas. Skirting finished the room edges.
07 · FIX-OUT
Robes and shower screens
Built-in robes were finished with sliding doors, hanging rails, shelving and drawers. A clear glass, black-framed shower screen was the last piece of the bathroom fix-out.
08 · HANDOVER
Keys to the owners
After the final details and clean-up, we handed over the Pomona home on 9 October 2026, and we’re told the owners are very happy with their new home.
The journey in numbers
Key milestones at a glance.
Day numbers count working days on site, starting with Day 1 on the building pad.
- Day 1: building pad prepared
- Day 6: concrete slab poured
- Days 7–11: steel wall and roof framing
- Day 27: lock-up
- Seven stages of interior fix-out
- 98 working days from slab to handover
- Handover: 9 October 2026