A steel frame home in Pomona, from slab to handover.

Follow this home from a freshly cleared block to the day the owners received the keys: slab, steel frame, lock-up on Day 27 and seven stages of interior fix-out, shown step by step.

Location
Pomona
Sunshine Coast Hinterland
Project
Two-bedroom home
90 m² internal floor area
Floor system
Concrete slab-on-ground
Steel frame on a reinforced slab
Status
Completed build
Handed over 9 October 2026

Pomona home / From the ground up

One home, every stage of the build.

Built on a reinforced concrete slab, this two-bedroom Pomona home pairs steel framing with Colorbond and fibre-cement cladding. Inside, sage-green kitchen cabinetry and timber-look flooring give the home a warm, understated finish. Follow the build from site preparation through to handover.

Digital renders and staging have been used to showcase this building.

From the building pad to handover.

From preparing the pad to handing over the keys. Fix-out stages are numbered in order rather than by day.

  1. 01 · DAY 1

    Preparing the building pad

    We cleared the vegetation and formed the building pad the home would sit on.

  2. 02 · DAY 2

    Positioning under-slab plumbing

    Plumbing went in beneath the future floor first, because it can’t be moved once the concrete is poured.

  3. 03 · DAY 3

    Preparing the slab area

    The slab area was prepared, ready for boxing, reinforcement and concrete.

  4. 04 · DAYS 4–5

    Installing boxing and reinforcement

    Boxing, the formwork around the edge, set the slab’s shape, and steel mesh went in to strengthen the concrete.

  5. 05 · DAY 6

    Pouring the concrete slab

    The concrete pour created the foundation the rest of the home is built on.

  6. 06 · DAYS 7–8

    Installing the steel wall frames

    Our team stood the steel wall frames on the slab, then connected and secured them ready for the roof.

  7. 07 · DAYS 9–11

    Building the roof structure

    Rafters, tie-downs and bracing formed the roof structure, with the tie-downs anchoring the roof to the frame. Scaffolding gave safe access around the home.

  8. 08 · DAYS 11–12

    Installing fascia and guttering

    Fascia went on along the roof edges, followed by the gutters and their flashings.

  9. 09 · DAYS 13–14

    Installing the roof

    The roof sheets went on and were fixed down, putting the main roof over the home.

  10. 10 · DAYS 15–16

    Lining the soffits

    Soffit lining finished the underside of the eaves.

  11. 11 · DAY 17

    Wrapping the wall frames

    Sarking, a protective wrap that helps keep moisture out of the walls, went around the steel frame ready for cladding.

  12. 12 · DAYS 18–20

    Installing the Colorbond wall cladding

    Corrugated Colorbond wall cladding started closing in the external walls.

  13. 13 · DAYS 21–24

    Adding cavity battens and fibre-cement cladding

    Cavity battens went on to hold the fibre-cement sheets and leave a drainage gap behind them. The sheets then finished the remaining walls.

  14. 14 · DAYS 25–26

    Completing barges and flashings

    Barge and flashing details sealed the roof edges, corners and joins, the last external work before lock-up.

The fix-out, stage by stage.

Seven stages, in the order the trades worked, then handover.

  1. 01 · FIX-OUT

    Plaster, doors and trims

    With the plaster finished, our carpenters fitted the internal door jambs, architraves, doors and handles. The rooms were then cleared of plaster dust and cleaned, ready for the next trades.

  2. 02 · FIX-OUT

    Kitchen cabinets and vanity

    The kitchen cabinets and bathroom vanity went in next. The kitchen features soft green cabinetry with black handles, drawers, pantry storage and spaces for the appliances.

  3. 03 · FIX-OUT

    Paint throughout

    Walls, ceilings, internal doors and trims were painted in a light, consistent finish, giving the interior a clean look before the final fixtures and surfaces went in.

  4. 04 · FIX-OUT

    Kitchen benchtops

    Light-coloured benchtops were fitted around the kitchen cabinetry in a wraparound layout, with room for food prep and the sink built in.

  5. 05 · FIX-OUT

    Bathroom tiling and fixtures

    The bathroom floor and shower walls were tiled in a neutral stone-look finish. Then the plumbing fixtures were installed.

  6. 06 · FIX-OUT

    Timber-look vinyl plank flooring

    Warm timber-look vinyl plank flooring runs through the kitchen, living areas and bedrooms, meeting the tiled bathroom areas. Skirting finished the room edges.

  7. 07 · FIX-OUT

    Robes and shower screens

    Built-in robes were finished with sliding doors, hanging rails, shelving and drawers. A clear glass, black-framed shower screen was the last piece of the bathroom fix-out.

  8. 08 · HANDOVER

    Keys to the owners

    After the final details and clean-up, we handed over the Pomona home on 9 October 2026, and we’re told the owners are very happy with their new home.

The journey in numbers

Key milestones at a glance.

Day numbers count working days on site, starting with Day 1 on the building pad.

  • Day 1: building pad prepared
  • Day 6: concrete slab poured
  • Days 7–11: steel wall and roof framing
  • Day 27: lock-up
  • Seven stages of interior fix-out
  • 98 working days from slab to handover
  • Handover: 9 October 2026