SOUTH COOLUM ROAD · COOLUM BEACH

Building a backyard POD in Coolum Beach.

See how 16 numbered construction days moved this Coolum backyard POD from site survey to external flashings and trims.

LOCATION

Coolum Beach

Sunshine Coast

PROJECT

Backyard POD

South Coolum Road

FLOOR SYSTEM

Concrete slab

Slab on ground

BUILD TIME

16 numbered days

Survey to external trims

THE BUILD / SOUTH COOLUM

From an established backyard to external lock-up.

The South Coolum POD was positioned within an established backyard. Pre-construction checks covered its building position, nearby services, ground levels and drainage.

The rear corner was cut down and the material used to build up the front. Crusher dust prepared a level base before under-slab plumbing and the reinforced concrete slab.

Across 16 numbered construction days, the POD progressed through its slab, TrueCore frame, roof, windows, TRIMDEK and Weathertex cladding, flashings and trims.

THE WORK BEHIND THE PROGRESS

An existing backyard. Details to resolve.

Position, levels, services and construction order all shaped how this POD was built.

01 / BUILDING POSITION

Starting in the right place.

A gridline survey established the POD’s position against the approved site plan, property boundaries and existing structures. The survey formed part of the certifier compliance documents.

02 / GROUND LEVELS

Preparing a level base.

The rear corner was cut down and the material used to fill the front. Crusher dust prepared the building pad for the slab.

03 / EXISTING SERVICES

Planning the connections.

Checks covered mains water, sewer, stormwater, power and the switchboard. Sunshine Coast Council inspected the under-slab plumbing before the slab was poured.

04 / NO-EAVES DESIGN

Getting the sequence right.

With no eaves, the rear windows and cladding were installed first so gutter flashing could go in before the roof.

05 / EXTERNAL CLADDING

Layering the external finishes.

TRIMDEK wrapped the main walls. Cavity battens prepared the entry for Weathertex cladding before the final flashings and trims.

BEFORE CONSTRUCTION

Checks that informed the build.

Before work began, the team reviewed the site, services, approvals and building position for the South Coolum POD.

  • Mains water location and capacity
  • Existing sewer and stormwater routes
  • Mains power and switchboard capacity
  • Property boundaries and setbacks
  • Building height requirements
  • Ground levels and drainage
  • Existing structures and site conditions
  • Approved plans and building position

FROM SURVEY TO EXTERNAL LOCK-UP

How the POD took shape.

Eight milestones group 16 numbered construction days, from the site survey to external flashings and trims.

Excavator preparing the building pad for a backyard POD in Coolum Beach

01 · DAY 1

Survey & site preparation

A gridline survey fixed the building position. Grass was cleared, the rear cut and the front filled before crusher dust levelled the pad.

Concrete slab being poured for the Coolum Beach backyard POD

02 · DAYS 2–4

Plumbing & concrete slab

Plumbing set-out established gridlines, levels and falls, followed by Sunshine Coast Council inspection before the slab. Piers, beams, formwork, step-downs and reinforcement were prepared, then the concrete was poured.

Steel roof framing panels installed over the TrueCore frame of the Coolum backyard POD

03 · DAYS 5–7

TrueCore frame & roof framing

TrueCore steel wall frames were installed, straightened and braced. Steel roof framing panels followed on Day 7.

Wall sarking installed around the steel frame of the Coolum backyard POD

04 · DAY 8

Wall sarking

Wall sarking wrapped the steel frame before the remaining exterior layers.

Rear cladding and gutter flashing installed before roofing on the Coolum POD

05 · DAYS 9–10

Rear windows, cladding & flashing

With no eaves, rear windows and cladding came first so gutter flashing could be installed before the roof.

Remaining windows being installed on the Coolum Beach backyard POD

06 · DAY 11

Roof sheeting, gutter & windows

The gutter, metal roof sheeting and remaining windows were installed on Day 11.

TRIMDEK wall cladding progressing around the Coolum backyard POD

07 · DAYS 12–13

TRIMDEK wall cladding

TRIMDEK metal wall cladding was installed around the POD.

Front of the Coolum backyard POD with entry cladding and glazed sliding door

08 · DAYS 14–16

Entry cladding & external trims

Cavity battens prepared the entry for Weathertex cladding. Final external flashings and trims completed the external lock-up sequence.

WHAT HAPPENS NEXT

Internal fit-out follows external lock-up.

By Day 16, the POD had reached external lock-up, with its roof, windows, cladding, flashings and trims in place. Internal services and fit-out, final inspection and handover follow this stage.