Building a backyard POD in Coolum Beach.

See how 16 numbered construction days moved this Coolum backyard POD from site survey to external flashings and trims.

LOCATION

Coolum Beach

Sunshine Coast

PROJECT

Backyard POD

South Coolum Road

FLOOR SYSTEM

Concrete slab

Slab on ground

BUILD TIME

16 numbered days

Survey to external trims

SOUTH COOLUM / FROM THE GROUND UP

From an established backyard to external lock-up.

The South Coolum POD was positioned within an established backyard. Pre-construction checks covered its building position, nearby services, ground levels and drainage.

The rear corner was cut down and the material used to build up the front. Crusher dust prepared a level base before under-slab plumbing and the reinforced concrete slab.

Across 16 numbered construction days, the POD progressed through its slab, TrueCore frame, roof, windows, TRIMDEK and Weathertex cladding, flashings and trims.

How the POD took shape.

Eight milestones group 16 numbered construction days, from the site survey to external flashings and trims.

Excavator preparing the building pad for a backyard POD in Coolum Beach

01 · DAY 1

Survey & site preparation

A gridline survey fixed the building position. Grass was cleared, the rear cut and the front filled before crusher dust levelled the pad.

Concrete slab being poured for the Coolum Beach backyard POD

02 · DAYS 2–4

Plumbing & concrete slab

Plumbing set-out established gridlines, levels and falls, followed by Sunshine Coast Council inspection before the slab. Piers, beams, formwork, step-downs and reinforcement were prepared, then the concrete was poured.

Steel roof framing panels installed over the TrueCore frame of the Coolum backyard POD

03 · DAYS 5–7

TrueCore frame & roof framing

TrueCore steel wall frames were installed, straightened and braced. Steel roof framing panels followed on Day 7.

Wall sarking installed around the steel frame of the Coolum backyard POD

04 · DAY 8

Wall sarking

Wall sarking wrapped the steel frame before the remaining exterior layers.

Rear cladding and gutter flashing installed before roofing on the Coolum POD

05 · DAYS 9–10

Rear windows, cladding & flashing

With no eaves, rear windows and cladding came first so gutter flashing could be installed before the roof.

Remaining windows being installed on the Coolum Beach backyard POD

06 · DAY 11

Roof sheeting, gutter & windows

The gutter, metal roof sheeting and remaining windows were installed on Day 11.

TRIMDEK wall cladding progressing around the Coolum backyard POD

07 · DAYS 12–13

TRIMDEK wall cladding

TRIMDEK metal wall cladding was installed around the POD.

Front of the Coolum backyard POD with entry cladding and glazed sliding door

08 · DAYS 14–16

Entry cladding & external trims

Cavity battens prepared the entry for Weathertex cladding. Final external flashings and trims completed the external lock-up sequence.

WHAT HAPPENS NEXT

Internal fit-out follows external lock-up.

By Day 16, the POD had reached external lock-up, with its roof, windows, cladding, flashings and trims in place. Internal services and fit-out, final inspection and handover follow this stage.

BEFORE CONSTRUCTION

Checks that informed the build.

Before work began, the team reviewed the site, services, approvals and building position for the South Coolum POD.

  • Mains water location and capacity
  • Existing sewer and stormwater routes
  • Mains power and switchboard capacity
  • Property boundaries and setbacks
  • Building height requirements
  • Ground levels and drainage
  • Existing structures and site conditions
  • Approved plans and building position